The launch slipway is a concrete ramp with 1/80 slope angle. From end of slipway to the Yangtse river there is a 60 m natural ground paved with gravel. Yangtse river is one of the most busy channel so our launch is strictly limited for the launch time and launch area by local Maritime Safety Administration.
The elevation of launching ramp end is 2 m and stern draft is 1.7 m so stern will not be refloated when it is launched at 120 m distance. To remedy the practical disadvantage our engineering team performed the detailed calculation of using ballast water to adjust the vessel trim angle during launch. At last 2000 tons ballast water was added into the bow cabin.
In the morning of May 21 our launch team begun to prepare all necessary work for the 40 m forward move and successional launch that must be completed within there hours. At 9 am the vessel transportation work started and got finished in one hour. According the plan this vessel will be launched at 12 am when the water reaches highest level in the day. Because of some emergency reason the local Maritime Safety Administration demanded the launch to be carried out at 10:30 am. So we got only 30 minutes to prepare the launch.

After the launch people found there was a gap at launch ramp conjunction position. Provided without the temporary reinforcement the part of ramp may collapsed during the launch.
It is a very urgent launch project. Our team depends on the scientific calculation and profound experience overcomed all practical disadvantages and did a great job. It is the fourth vessels launched by our company in this month . Airbag ship launching is proved to be successful and flexible in deficient conditions.